Test 2: Launch Rehearsal, 4/13 or 4/14

Required: 

  • Verification checklists for rigorous checking of proper assembly (should be very simple and clear and have photos)
  • Flight team assignments

Scope: 

  1. Pack tools & GSE listed in assembly checklists
  2. Pre-charge cameras, payload, and ALL altimeter batteries
  3. Transport only those tools to the hangar
  4. Assemble Hermes II in the hangar
    1. Log & acquire any missing tools/GSE
  5. Put in "Final Integration" state
  6. Finish integration in hangar

...