  • Completed Avionics + Recovery Ground Test without cameras
  • Refined packing lists 

Test 2: Launch Rehearsal, 4/13

...

Required: 

  • Verification checklists for rigorous checking of proper assembly (should be very simple and clear and have photos)
  • Flight team assignments

...

  1. Pack tools & GSE listed in assembly checklists
  2. Pre-charge cameras, payload, and ALL altimeter batteries
  3. Transport only those tools to the hangar
  4. Assemble Hermes II in the hangarLog & acquire any missing tools/GSE
  5. Put in "Final Integration" state
  6. Finish integration in hangar

Goals:

  • Log single point failure locations
  • Refine packing lists with finished flight hardware
    • Add missing tools & materials
    • Add missing flight parts
  • Log Assembly times
    • Overall start/finish
    • By subsystem
    • Final integration
  • "Wish List" for additional GSETest camera operation while integrated
  • Practice rocket integration in alternate locationhangar

Test 3: Launch Rehearsal, 4/20, 4/27 and/or 5/4

...