Summary Status
- *12/22/08 * 2 out of 16 tasks in Milestone "Cluster"
- 12/12/08 "Feature Complete" Milestone met.
- 8/15/08 "Preview Release" Milestone met.
- 7/25/08 "Basic" Milestone met.
- 6/30/08 "Core" Milestone met.
- 3/18/08 "Infrastructure" milestone met.
- 12/12/08 "Feature Complete" milestone met.
...