- 12/22/08 2 out of 16 tasks in Milestone "Cluster"
- 12/12/08 "Feature Complete" Milestone met.
- 8/15/08 "Preview Release" Milestone met.
- 7/25/08 "Basic" Milestone met.
- 6/30/08 "Core" Milestone met.
- 3/18/08 "Infrastructure" milestone met.
- 12/12/08 "Feature Complete" milestone met.
Third Party software policies and process are being reviewed in the document 3rd Party Software under Athena 10
Bugs/Issues with Athena 10 are tracked in the Athena 10 Jira
The issues are organized in a prioritized punch list .
Bugs/Issues relevant to the broader debathena scope are tracked in the Debathena Trac
Third Party software policies and process are being reviewed in the document 3rd Party Software under Athena 10
The detailed tasks and features are detailed in the Athena 10 Technical Plan .
...