  • Communication
    • No paper handouts were generated during this project. Overhead presentations, emails, system messages and the wiki were effectively utilized.
    •   updates were timely and informative
  • Schedule
    • Cut-over down time had no practical impact on Singapore operation.
    • The overall project and each of it's major phases were completed on time inline with the original plan.
    •   contingencies were needed and utilized
  • Governance
    •  
  • Process
    •  
  • Project Management
    •  
  • Risk Management
    •  Back-up managers
    • contingency time is a must 
  • Sponsorship
    •  
  • Staffing Levels
    •  
  • Teamwork
    •  
  • Other
    •  

Challenges - Other

  • Communication
    •   steering committee mtgs could be scheduled around milestones
  • Schedule
    •  leave time for pre-development systems preparation
    • SAP delivers the packs for analysis in October
    •  
  • Governance
    •   Others are welcome to participate on the steering committee.
  • Process
    •  
  • Project Management
    • Recurring nature of this project could allow for on-the-job training for future managers.  A new role (eg. project coordinator) could be defined to both prepare next year's leader fill in as back-up as needed.
    •  
  • Risk Management
    •  
  • Sponsorship
    •  
  • Staffing Levels
    •  
  • Teamwork
    •  
  •  Other
    •