Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Communication
    • Meeting notes on the wiki were not always accurate
  • Schedule
    • Late-occurring problem with Finance tested contingency 
    • Revise schedule to allow extra time for problems/long-duration steps
    • Schedule for preparation of different systems should reflect available resources on each system
    • Addition of enhancement packs extended time for system preparation more than expected
    • Benchmark enhancement pack application before project starts (if possible)
  • Governance
    •  
  • Process
    • Late delivery of high-use transactions & programs for analysis/division was difficult & time-consuming
    • Keep identification of critical transactions & reports for reference next year - include reference to test scripts
  • Project Management
    • Need individual assigned to monitor issues in RT queue
  • Risk Management
    • Need development & testing environments for items that must go into production shortly after go-live
    • Better definition of project freeze and difference between development freeze and transport freeze
  • Sponsorship
    •  
  • Staffing Levels
    • QA  could play a more predominant role i.e. back-up manager
    • Project manager should be identified earlier and have fewer testing responsibilities
  • Teamwork
    •  
  •  Other
    •  

Additional input for SAIS team members

Wins

  • Including more detail on the Action Log and implementation plan than in the past
  • Everyone stepped up to meet the shortened deadlines by working extra hours but this shouldn't become a habit
  • Second year of SIT execution
  • Now have two years of SIT scripts
  • Some business owners / users updated scripts on their own
  • Aliases worked well again this year

Challanges

  • Implement the support packs and enhancements in a sandbox/prototype environment first to get a better idea of the impact and time needed
  • Start review/analysis of the support packs already received earlier - don't perform testing until all are received
  •  A spreadsheet is not the best tool for keeping the information needed for testing; a DB or other tool would be helpful
  • Have an environment with the changes applied available so development can continue
  •  During the implementation, please don't move status calls earlier without at least an hour's notice
  • Extended team meetings were not conducted frequently enough
  • Information dissemination was pushed down to the individual functional teams, didn't come from one place
  • Many individual test scripts still not updated
  • I had responsibility for approving UAT for some business areas due to staff turnover
  • Confusion about when UAT ended
  • Confusion about what could be tested during period end closing
  • Confusion about the intention of SIT / UAT
  • Business owners were told they did not have to test during UAT; they could accept the results of SIT as UAT; created a mess that had to be re-communicated at length
  • Not enough communication
  • Scheduling of users during UAT wasn't done consistently; given a time period and a deadline and told to meet it; created lots of uncertainty around the deadline