Support Pack Project

  • Panel
      • Now - October - Plan, create master script catalog, improve test scripts, move pending work to production
        • 10/05/2009 - Last date to implement projects until freeze ends on 12/24/2009 (Except Open Enrollment & Union Structures)
        • 10/19/2009 - Production snapshot at end of day - will be used to refresh dev & test environments 
        • 10/22/2009 - Last date to implement support & enhancement changes until freeze ends on 12/24/2009
        • 11/03/2009 - 11/08/2009 Unit Test
        • 11/09/2009 - 11/22/2009 System Integration Test (SIT Task List)
        • 11/23/2009 - 12/09/2009 User Acceptance Test
        • 12/11/2009 - 12/13/2009 Golive Weekend
        • 12/24/2009   Development Freeze ends

Could combining Systems Integration Testing with User acceptance testing become the rule vs. an option?

...