Schedule - The project schedule was primarily based on prior years experience and it's start and finish are restricted to a window that is dependent on availability of SAP packs and must be completed before the start of the new Payroll year. Although not entirely flexible, there might be some opportunities to change details within our schedule.

Panel

Support Pack Project

  • Panel
        • 10/05/2009 - Last date to implement projects until freeze ends on 12/24/2009 (Except Open Enrollment & Union Structures)
        • 10/19/2009 - Production snapshot at end of day - will be used to refresh dev & test environments 
        • 10/22/2009 - Last date to implement support & enhancement changes until freeze ends on 12/24/2009
        • 11/03/2009 - 11/08/2009 Unit Test
        • 11/09/2009 - 11/22/2009 System Integration Test (SIT Task List)
        • 11/23/2009 - 12/09/2009 User Acceptance Test
        • 12/11/2009 - 12/13/2009 Golive Weekend
        • 12/24/2009   Development Freeze ends

Could combining Systems Integration Testing with User acceptance testing become the rule vs. an option?

...