How significant was the impact of bringing down production at noon on the Friday of the cut-over weekend?

Project Plan

      • (September - October) - Plan, create master script catalog, improve test scripts, move pending work to production
      • 10/05/2009 - Last date to implement projects until freeze ends on 12/24/2009 (Except Open Enrollment & Union Structures)
      • 10/19/2009 - Production snapshot at end of day - will be used to refresh dev & test environments 
      • 10/22/2009 - Last date to implement support & enhancement changes until freeze ends on 12/24/2009
      • 11/03/2009 - 11/08/2009 Unit Test
      • 11/09/2009 - 11/22/2009 System Integration Test (SIT Task List)
      • 11/23/2009 - 12/09/2009 User Acceptance Test
      • 12/11/2009 - 12/13/2009 Golive Weekend
      • 12/24/2009   Development Freeze ends

Wins - Schedule

  •  

Challenges - Schedule

...