November 2, 2009 Core Team

  1. Unit Test Schedule? - SF3 Upgrade will not complete until this evening & SF2 by tomorrow evening or Wednesday morning. - Impact?
    • When can SPAU & action log activities begin?
    • How many days are required for UNIT test / from where in the plan to we subtract the time?
  2. Unit test execution
    • Consolidated list will be split up by teams
    • Daily updates required - If updated spreadsheets can not be posted to the Wiki daily, a percentage complete should be communicated to the PM and the end of each day.
    • Issues/Errors must be logged in the SAP:: Test Issues queue, email = saptest@help.mit.edu.
    • The spreadsheets will be the official test log - Results (pass/fail) and testers name must be filled in for completion of this test phase.

November 4, 2009 Steering Committee 9-10am W92-240 Riverside

...