  1. Unit Test Schedule? - SF3 Upgrade will not complete until this evening & SF2 by tomorrow evening or Wednesday morning. - Impact?
    •  Update to SF3 should be completed tonight by 10:00pm.
    • SPAU - generate tonight. 
    • Tomorrow am.  Rich K. will apply SAP notes. Should take 2hrs
      • When can SPAU & action log activities begin? - Other prep. activities? (interfaces, queued data files, etc.)
        • Mods and SPAU also will start Tuesday a.m. and complete by 3:00 pm 
      • How many days are required for UNIT test / from where in the plan do we subtract the time?
        • The project plan's schedule can not be changed. We must complete unit testing by Monday 11/9.
        • SF2 will be available for testing on Wednesday by aproximatly 11:00
      amn
        • am.
        • The action log will be executed (1 - 2hrs)
        •  Unit test start - 11am Wednesday (original scheduled to start Tue 8am).
  2. Unit test execution SF2 Unit test execution
    • SF3 was offered as an alternative environment to begin unit testing however the prep.(i.e. authorizations), results logging, and issue resolution were reasons to keep unit testing confined to one system.
    • SF2 update should be completed by late Tuesday or early Wednesday a.m.(8:00)
    • A Check-in with the core team is scheduled for Tuesday at 3:00 to confirm we are on track.
    •  
      • Consolidated list will be split up by teams
    #*
      • Daily updates required - If updated spreadsheets can not be posted to the Wiki daily, a percentage complete should be communicated to the PM and the end of each day.
      • Issues/Errors must be logged in the SAP:: Test Issues queue, email = saptest@help.mit.edu.
      • The spreadsheets will be the official test log - Results (pass/fail) and testers name must be filled in for completion of this test phase.
  1. Time Sheets
    • We need to stay current with our time allocated to this project
    • confirm that SAIS project team members have project related tasks assigned in Daptive
  2. Testers
    • SAIS should have their same authorizations in SF2. Let, Ken know if there are additional authorizations needed.
    • We are looking for the complete list of business testers for UAT and the names of those who would need to be unlocked for SIT.
  3. December 24th Institute holiday - was to be the 1st day for resuming normal transports. Can this change to the 23rd?

...