- Status Updates for Project Plan -
- - SH3 practice update- complete 10/16 (done)
- - PS1 snapshot for SH2- taken 10/19 (done)
- - SFK kernel update - complete 10/19 (done)
- - SFK oracle upgrade - complete 10/19 (done)
- - Pull & store DW extracts - 10/20 (done)
- - SFK support packs - start 10/26 (dates require change) Questions regarding system downtime and when the earliest we can start SF2 update. Can not begin until after open enrollment transports are applied. Question for Julie is if Tuesday is an option? Unit testing would start on the 11/3. If we can not begin unit testing on 11/3 it would be prefered that we take time needed away from SIT.
- Unit Test - Waiting for team updates - decide how to use spreadsheet for logging results - All updates have been made to the exception list of 430+. Ken will made the chages to the consolodated spreadsheet. The plan will then be to split the list up by team for execution of the Unit test.
- Transports - We are currently in development freeze -
- - Critical transports
- - Synchronzed transports (i.e. Open Enrollment)
- - Pending transports - List?
- Developer Planning Meeting - Wai Ming - Status - Since there is only ONE day allocated for the MOD in SF3 and we are running a very tight schedule, we will NOT move any MOD to the Enhancement Framework in the Support Pack 2009 project.
- SAPbiz this week - Message regarding user participation in SIT
...