Important Dates 

  • 11

...

  • /20 to 12/10 - User acceptance testing

...

  • All testing done by 12/5

...

  • 12/8 - 12/10 for issue retesting and financial closing

...

  • (Don't wait until the end to test)

...

  • 12/12 - Go / No Go Decision

...

  • Based on results of user acceptance testing

...

  • , Business owners will indicate their approval and acceptance of testing

o12/13 to 12/15 - Go live weekend
nProduction will be down from 6pm Friday evening until 6am Monday morning
o12/22 - Drop dead date for updating production with support packages
nWe have to be done by this date
o12/23 - first 2009 payroll run