Presentations
Meeting Notes
...
09/13/2010 - Core Team Meeting
In attendence: core team members
Agenda
- Set schedule date and time for core team meetings
- consensus to meet Monday's at 10:00-11:00am for the duration of the project; location W92:Downtown Crossing
- Review of detail project plan
- discussion around practice system
- discussion around transports
- discussion around testing
- discussion around freeze
- Next steps
- focus on test plan
- confirm NW 7.0 EHP 2 availability & compatibility (Bart & Ron are pursuing with SAP)
- focus on moving current development work to production
- SAPbiz meeting on 9/22/2010
09/09/2010 - IS&T Kickoff Meeting
...