Role | Members | Primary Responsibilities | Communication |
|---|
Sponsor | Bart Dahlstrom, Associate Director, IS&T Admin Systems | - Provide overall direction, goals & funding
- Approve charter, scope, milestones, budget
- Remove obstacles
| - Monthly written status report
- Invitation to attend steering committee 1st Monday each month
|
Steering Committee | - Bart Dahlstrom (Associate Director, IS&T Admin Systems)
- Bill VanSchalkwyk (Managing Director, EHS Programs)
- Gerry O'Toole (Director of Financial Operations)
- John Doyle (Assistant Director, Procurement)
- Magdalene Lee (Assistant Controller)
- Marty Dugal (Assistant Director, Facilities Operations)
- Mary Weiss (Associate Director, IS&T Data Management)
- Steve Buckley (Associate Director, IS&T Sys Engineering)
- Wayne Turner (Director of Bus. Partnerships & Operations)
| - Provide oversight, schedule resources
- Define roles & responsibilities
- Set standards, guidelines, processes, metrics
- Remove obstacles, resolve issues
- Approve go/no go decision
| - Monthly steering committee meetings - October - January
- 10/3/2011
- 11/7/2011
- 11/28/2011 (Tentative) Go/No Go decision
- 1/3/2012 (Tentative) Post project review
|
Project Manager | Frank Quern | - Complete project on time, on budget
- Manage overall project: plan, track progress, resolve issues, escalate when necessary, ...
- Communicate: with project team, sponsors, steering committee, stakeholders, broader community
- Ensure appropriate business and IS&T resources are assigned to project tasks
- Coordinate work among project teams, data warehouse, OIS, IS&T help desk, ...
| |
Transport Coordinator | John Tuttle | - Define process, lists, tracking procedures
- Plan and track effort to move pending transports to production before freeze
- Manage any critical transports during freeze to ensure they are included in upgrade
- Manage all transports related to support pack project
| |
Core Team: Technical Leads | - Basis/security - Ron Parker
- Basis/authorizations - George Petrowsky
- ABAP, ITS - Wai-Ming Li
- Web - Rich Murphy
- DW - Scott Thorne
| - Prepare environments
- Apply support packs related to support pack project * Execute SF3 modification testing; Resolve & retest issues
- Unit test (joint with functional team)
- Analyze & resolve issues
- Execute cutover activities
- Coordinate work of basis team and developers
| - Weekly core team meeting - Monday 9:00-10:00 W92-North Station starting 9/19/2011
- Kick off meeting TBD (week of 9/12)
- sap-upgrade-core@mit.edu
- project wiki
|
Core Team: Functional Leads | - HR/Payroll Testing Coordinator - Mary Donovan
- Benefits
- Compensation
- Human Resources (Service Center)
- Payroll
- Pension Payroll
- Enterprise Learning
- AP/EHS/FI/PO Testing Coordinator - Ken Le Vie
- AP
- EHS
- Travel
- Procurement (xECAT3)
- Facilities
- Parking
- ECAT3
- SMART (Singapore)
- Functional Team leads
- Frank Quern (HR/Pay)
- Siobhan Cunnigham (AP/EHS/FI/PO)
| - Unit testing (joint with technical team, track and report process)
- System integration testing (define scope, update & execute scripts, track and report progress)
- User acceptance testing (assist if needed)
- Serve as primary liaison with business owners
- Analyze & resolve issues
- Execute cutover activities
- Coordinate work of business analysis and business owners
| - Weekly core team meeting - Monday 9:00-10:00 W92-North Station starting 9/19/2011
- Kick off meeting TBD (week of 9/12)
- sap-upgrade-core@mit.edu
- project wiki
|
Core Team: QA | - Wendy Bastos
- Kevin Muti
| - Define & communicate process & templates to manage test cases
- Set standards for quality assurance process
- Oversee QA work on the project
| - Weekly core team meeting - Monday 9:00-10:00 W92-North Station starting TBD
- Kick off meeting TBD (week of 9/12)
- sap-upgrade-core@mit.edu
- project wiki
|
Extended Team | - ist-sap@mit.edu
- which includes all IS&T staff supporting SAP.
- Conact Frank Quern, Kevin Lyons or Bart Dahlstrom if you are not on the list and think you should be.
| - Perform tasks as directed by core team leads
| - Kick off meeting in September, before SAPbiz kickoff
- ist-sap@mit.edu
- project wiki
|
Business Owners | - GL Reporting, JV - Magdalene Lee, TBD
- HR/Payroll - Leslie Wright
- HR/Benefits - Anne Lafleur/TBD, Diane Johnston
- Facilities - Lisa St. Croix
- Stockroom - Tammy Doyle
- EHS - Laurie Veal
- Spons. Billing - TBDMeg Benson, Pam Schickling
- Gen AR - Donna Cairns
- Cashiers - Cheryl Whelan
- Property: Kevin Milligan
- Fund Centers: Peggie McGrath
- IST Telecom: Allan Wallace
- Tech Review: Jim Coyle
- AP - John Larkin, Wayne Dwyer
- Procurement - Scott BallJohn Doyle, Sara Malconian
- eCAT - Scott Ball
- Travel - Kathy McGrath
- SMART - John Larkin, TBDMagdalen Lee, Sara Malconian
- OSP - Steve Dowdy
- OBO - Rob Slauzis
- Pcard - Kathy McGrath, Kim Harmon
- EL - Jane White
| - Perform user acceptance testing (define scope, update & execute scripts, retest as needed)
- Report issues via RT
- Train end users if any changes are discovered (none anticipated)
- Sign-off that updated system is accepted for your business area and support packs can move to production
- Perform any business cut-over activities
- Validate production system (define criteria, validate system)
| - Kick off meeting @ 9/14/2011 SAPbiz meeting
- Every other week at SAPBiz or as required
- Meeting minutes and updates available on this wiki
- project wiki
|