Role   | 
 Members   | 
 Primary Responsibilities   | 
 Communication   | 
 Sponsor   | 
 Bart Dahlstrom, Associate Director, IS&T Admin Systems   | 
	- Provide overall direction, goals & funding
 
	- Approve charter, scope, milestones, budget
 
	- Remove obstacles
 
 
 | 
	- Monthly written status report
 
	- Invitation to attend steering committee 1st Monday each month
 
 
 | 
 Steering Committee   | 
	- Bart Dahlstrom (Associate Director, IS&T Admin Systems)
 
	- Bill VanSchalkwyk (Managing Director, EHS Programs)
 
	- Gerry O'Toole (Director of Financial Operations)
 
	- John Doyle (Assistant Director, Procurement)
 
	- Magdalene Lee (Assistant Controller)
 
	- Marty Dugal (Assistant Director, Facilities Operations)
 
	- Mary Weiss (Associate Director, IS&T Data Management)
 
	- Steve Buckley (Associate Director, IS&T Sys Engineering)
 
	- Wayne Turner (Director of Bus. Partnerships & Operations)
 
 
 | 
	- Provide oversight, schedule resources
 
	- Define roles & responsibilities
 
	- Set standards, guidelines, processes, metrics
 
	- Remove obstacles, resolve issues
 
	- Approve go/no go decision
 
 
 | 
	- Monthly steering committee meetings - October - January
 
	- 10/3/2011
 
	- 11/7/2011
 
	- 11/28/2011 (Tentative) Go/No Go decision
 
	- 1/3/2012 (Tentative) Post project review
 
 
 | 
 Project Manager   | 
 Frank Quern   | 
	- Complete project on time, on budget
 
	- Manage overall project: plan, track progress, resolve issues, escalate when necessary, ...
 
	- Communicate: with project team, sponsors, steering committee, stakeholders, broader community
 
	- Ensure appropriate business and IS&T resources are assigned to project tasks
 
	- Coordinate work among project teams, data warehouse, OIS, IS&T help desk, ...
 
 
 | 
   | 
 Transport Coordinator   | 
 John Tuttle   | 
	- Define process, lists, tracking procedures
 
	- Plan and track effort to move pending transports to production before freeze
 
	- Manage any critical transports during freeze to ensure they are included in upgrade
 
	- Manage all transports related to support pack project
 
 
 | 
   | 
 Core Team: Technical Leads   | 
	- Basis/security - Ron Parker
 
	- Basis/authorizations - George Petrowsky
 
	- ABAP, ITS - Wai-Ming Li
 
	- Web - Rich Murphy
 
	- DW - Scott Thorne
 
 
 | 
	- Prepare environments
 
	- Apply support packs related to support pack project * Execute SF3 modification testing; Resolve & retest issues
 
	- Unit test (joint with functional team)
 
	- Analyze & resolve issues
 
	- Execute cutover activities
 
	- Coordinate work of basis team and developers
 
 
 | 
	- Weekly core team meeting - Monday 9:00-10:00 W92-North Station starting 9/19/2011
 
	- Kick off meeting TBD (week of 9/12)
 
	- sap-upgrade-core@mit.edu
 
	- project wiki
 
 
 | 
 Core Team: Functional Leads   | 
	- HR/Payroll Testing Coordinator - Mary Donovan
	
		- Benefits
 
		- Compensation
 
		- Human Resources (Service Center)
 
		- Payroll
 
		- Pension Payroll
 
		- Enterprise Learning
 
	 
	 
	- AP/EHS/FI/PO Testing Coordinator - Ken Le Vie
	
		- AP
 
		- EHS
 
		- Travel
 
		- Procurement (xECAT3)
 
		- Facilities
 
		- Parking
 
		- ECAT3
 
		- SMART (Singapore)
 
	 
	 
	- Functional Team leads
	
		- Frank Quern (HR/Pay)
 
		- Siobhan Cunnigham (AP/EHS/FI/PO)
 
	 
	 
 
 | 
	- Unit testing (joint with technical team, track and report process)
 
	- System integration testing (define scope, update & execute scripts, track and report progress)
 
	- User acceptance testing (assist if needed)
 
	- Serve as primary liaison with business owners
 
	- Analyze & resolve issues
 
	- Execute cutover activities
 
	- Coordinate work of business analysis and business owners
 
 
 | 
	- Weekly core team meeting - Monday 9:00-10:00 W92-North Station starting 9/19/2011
 
	- Kick off meeting TBD (week of 9/12)
 
	- sap-upgrade-core@mit.edu
 
	- project wiki
 
 
 | 
 Core Team: QA   | 
	- Wendy Bastos
 
	- Kevin Muti
 
 
 | 
	- Define & communicate process & templates to manage test cases
 
	- Set standards for quality assurance process
 
	- Oversee QA work on the project
 
 
 | 
	- Weekly core team meeting - Monday 9:00-10:00 W92-North Station starting TBD
 
	- Kick off meeting TBD (week of 9/12)
 
	- sap-upgrade-core@mit.edu
 
	- project wiki
 
 
 | 
 Extended Team   | 
	- ist-sap@mit.edu 
	
		- which includes all IS&T staff supporting SAP.
 
		- Conact Frank Quern, Kevin Lyons or Bart Dahlstrom if you are not on the list and think you should be.
 
	 
	 
 
 | 
	- Perform tasks as directed by core team leads
 
 
 | 
	- Kick off meeting in September, before SAPbiz kickoff
 
	- ist-sap@mit.edu
 
	- project wiki
 
 
 | 
 Business Owners   | 
	- GL Reporting, JV - Magdalene Lee, Joy Matos
 
	- HR/Payroll - Leslie Wright
 
	- HR/Benefits - Anne Lafleur/TBD, Diane Johnston
 
	- Facilities - Lisa St. Croix
 
	- Stockroom - Tammy Doyle
 
	- EHS - Laurie Veal
 
	- Spons. Billing - Meg Benson, Pam Schickling
 
	- Gen AR - Donna Cairns
 
	- Cashiers - Cheryl Whelan
 
	- Property: Kevin Milligan
 
	- Fund Centers: Peggie McGrath
 
	- IST Telecom: Allan Wallace
 
	- Tech Review: Jim Coyle
 
	- AP - John Larkin, Wayne Dwyer
 
	- Procurement - John Doyle, Sara Malconian
 
	- eCAT - Scott Ball
 
	- Travel - Kathy McGrath
 
	- SMART - John Larkin, Magdalen Lee, Sara Malconian
 
	- OSP - Steve Dowdy
 
	- OBO - Rob Slauzis
 
	- Pcard - Kathy McGrath, Kim Harmon
 
	- EL - Jane White
 
 
 | 
	- Perform user acceptance testing (define scope, update & execute scripts, retest as needed)
 
	- Report issues via RT
 
	- Train end users if any changes are discovered (none anticipated)
 
	- Sign-off that updated system is accepted for your business area and support packs can move to production
 
	- Perform any business cut-over activities
 
	- Validate production system (define criteria, validate system)
 
 
 | 
	- Kick off meeting @ 9/14/2011 SAPbiz meeting
 
	- Every other week at SAPBiz or as required
 
	- Meeting minutes and updates available on this wiki
 
	- project wiki
 
 
 |