Now thru the end of October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
10/dd/
...
2013 – SAP release of year end base level support pack
10/dd/2013 – Production outage; DB & OS upgrade
10/dd/
...
2013 - End of day production snapshot to be used to refresh test environments
10/
...
dd/
...
2013 - Development Freeze begins
...
11/
...
dd/
...
2013 - Last date to implement support & enhancement changes until freeze ends on 12/
...
dd/
...
2013
...
10/
...
dd/
...
2013 - 11/
...
dd/
...
2013 Unit test
...
11/
...
dd/
...
2013 - 11/
...
dd/
...
2013 System Integration Test
12/
...
7/
...
2013 - 12/
...
8/
...
2013 Go-live weekend!
12/5/2012 - Development Freeze ends