High-Level Timeline


Now thru the end of October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
10/dd/2013 – SAP release of year end base level support pack
10/dd/2013 – Production outage; DB & OS upgrade
10/dd/2013 - End of day production snapshot to be used to refresh test environments
10/dd/2013 - Development Freeze begins
11/dd/2013 - Last date to implement support & enhancement changes until freeze ends on 12/dd/2013
10/dd/2013 - 11/dd/2013 Unit test

11/dd/2013 - 11/dd/2013 System Integration Test

(green star) 12/7/2013 - 12/8/2013 Go-live weekend!

(tick) 12/5/2012 - Development Freeze ends