  1. Pack tools & GSE listed in assembly checklists
  2. Pre-charge cameras, payload, and ALL altimeter batteries
  3. Stow in containers that will go to LA
  4. Pack coolers of food, tents, tables
  5. Transport only packed tools to the hangar
  6. Assemble Hermes II in the hangar
    1. forgotten tools, missing parts require time delays to be recorded
  7. Put in "Final Integration" state
  8. Go to sleep, wake up early the next morning
    1. Depart hangar at 7am
  9. Collect everyone at the hangar prior to going to Field A
    1. If people sleep in, they are "sick" and cannot take on the usual role
  10. Set up tables & test stand as "launch tower" on Briggs prior to transport (simulate "FAR")
  11. Pack a car with rocket & GSE, drive to Kresge oval
  12. Transport to Briggs Field with GSE
  13. Perform Integration & Prelaunch procedures (except igniter, incl. raising to vertical)
  14. Verify telemetry in launch ready configuration
  15. Perform "rocket take down" procedures 
  16. Change out a battery batteries in the AV Bay, LE, and NC
  17. Bring rocket back to launch-ready configuration, verify telemetry
  18. Perform "rocket take down" procedures 
  19. Perform "Launch" with telemetry and video during a ground test
  20. Recommended: Recovery team walks 2 miles with backpacks & of water & snacks
  21. Rest of team does launch site cleanup
  22. Use recovery procedures to pick up & safe the rocket
  23. Recommended: Recovery team walks 2 miles with the rocket and backpacks & of water & snacks
  24. Transport back to lab
  25. Log all data
  26. Report estimated total time (with delays)

...