  1. Pack tools & GSE listed in assembly checklists
  2. Pre-charge cameras, payload, and ALL altimeter batteries
  3. Stow in containers that will go to LA
  4. Pack coolers of food, tents, tables
  5. Transport only those tools to the hangar
  6. Assemble Hermes II in the hangar
    1. forgotten tools require time delaysmissing parts require  require time delays to be recorded
  7. Put in "Final Integration" state
  8. Go to sleep, wake up early the next morning
  9. Collect everyone at the hangar prior to going to Field A
    1. If people sleep in, they are "sick" and cannot take on the usual role
  10. Set up stuff prior to transport (simulate "FAR")
  11. Transport to Briggs Field A with GSE, including test stand as "launch tower"
  12. Perform Integration & Prelaunch procedures (except igniter, incl. raising to vertical)
  13. Verify telemetry in launch ready configuration
  14. Perform "rocket take down" procedures 
  15. "Launch" with telemetry and video during a ground test
  16. Recovery team walks 2 miles with ballasted backpacks
  17. Rest of team does launch site cleanup
  18. Use recovery procedures to pick up & safe the rocket
  19. Recovery team walks 2 miles with the rocket and backpacks
  20. Transport back to lab
  21. Log all data
  22. Report estimated total time (with delays)

Goals: 

  • Test flight team with realistic & adverse launch environment
  • Train support people

...