  • Put Teflon tape on the pressure transducer and set up the load cell or any other transducers you may have.

  • Use your hands or some tools to tighten/untighten the bolts of the test stand as needed.

  • Hit stakes into the ground with a hammer or mallet.

  • Attach our ratchet straps to the test stand and stakes (don’t tighten yet).

  • Attach our transducer wires to the DAQ in its protective box.

  • Set up the cameras.

  • Place the motor in the test stand and attach the transducers.

  • Begin to tighten the bolts as needed to secure motor.

  • Start to tighten the ratchet straps till the stand is snug in place.

  • Begin collecting data as a test (just checking that DAQ works).


DATA ANALYSIS SCRIPT 2022 ONWARDS: Data_Analysis_Generic.m

 

 

 

Procedure:

Now, we will talk about the static firing procedures. This is a list of actions that must be followed in the following order:

...