Although all the functionality is available for Public Cluster deployment, the components are un-bundled and can be mixed and matched into packagings radically different from the collections that have historically been viewed as "the way Athena is".

Summary Status

  • *12/22/08 * 2 out of 16 tasks in Milestone "Cluster"
  • 12/12/08 "Feature Complete" Milestone met.
  • 8/15/08 "Preview Release" Milestone met.
  • 7/25/08 "Basic" Milestone met.
  • 6/30/08 "Core" Milestone met.
  • 3/18/08 "Infrastructure" milestone met.
  • 12/12/08 "Feature Complete" milestone met.

...