You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 23 Next »

This is the section for the overall Athena Program -- various projects associated with Athena renewals, hardware and software upgrades, etc.  Program Manager is Bill Cattey.

Projects

Project

Start Date

Estimated Completion Date

Status

Notes

Debathena

ON TRACK

While the initial project to deploy Debathena (f/k/a Athena 10) to the public clusters is now complete, Debathena remains an ongoing project under active development.

Desktop Solaris Sunset

1-FEB-2010

ON TRACK

Outreach to customers regarding decomissioning of Solaris as an Athena platform.

Zephyr to Jabber Migration

RAMP UP

XMPP/Jabber seems the way of the future. Investigate replacing Zephyr with Jabber.

Completed Projects

Completed projects may be viewed on the Project Archive page.

  • No labels