Lessons learned notes (IS&T session held 01/28/2011)

Project Organization

  • Steering Committee
    • - Based on feedback from last years Support Pack Project the Steering Committee was expanded to include more BPO representation.
    • - The general consesus was this was a good idea as in prior years BPO representation was inadequate.
    • - Should create an email list for committee members.
  • Core Team
    • - Worked well; representation was adequate.
    • - Testing coordinators made organizing work easier.
    • - QA representation (a point person) on the team proved beneficial to the QA team and the project as a whole.
    • - Transport coordinator continues to play an important role.

Planning/Schedule

  • Adequate for the project
  • Validation by BPO should be tested before cutover weekend (some testers where not the normal executers or the transactions being tested)
  • Remote cutover testers should test connections to system before cutover weekend

Testing

  • Unit Testing
    • Keep the 5 day unit test window - new functionality has been introduced; the time for testing/resolving issues is needed
    • We used an Access db to store a catalog of the transactions we tested by whom and compared to last year
      • concept was good and has value
      • the execution was rushed (the db was not really "production" ready)
      • the tool was a little klugy 
      • better solution should be explored (within SAP, within SM)
    • Should consider storing unit test cases in QC to promote a single consistant cataloging approach
  • SIT/UAT Testing
    • QC - central repository for catalog of test cases
      • Worked well as a catalog for test cases 
      • Great for monitoring execution status
      • Saved preparation time of test "lab" for BAs (cases already in QC and available for use)
    • Test cases for the most part were not ready for QC formatting
      • Cases are/were designed for printing
      • A focused effort updating the cases to be QC formated would be beneficial to the process (requires resources)
      •  

Transports

  • Transport freeze
  • Critical transport process

Communication

  • Project wiki
    • Great for dates and status, assuming it is kept up-to-date
    • Was used as reference by all IS&T participants
    • Could be used to report cutover status in addition to status phone line, emails, etc ...
  • Status line was used by IS&T staff
  • Frequency of meetings
    • Core Team Monthly meetings - adequate and focused
    • Functional BA - daily meetings during testing phases kept teams focused
  • Did people feel they knew what was going on and what was expected of them? - Yes
  • Other
    • Could utilize WebEx - in light of IS&T moves

Cutover

  • Communication
    • The Plan itself
    • emails- Subscribe to email list of core team during the project/during cutover (watcher list could be added)** phone
    • conference line - use WebEx to allow more participants on the call
    • validation steps
  • Execution
    • For the most part ran smoothly - went live slightly ahead of schedule
    • Cutover plan contained necessary details for successful execution
  • Other
    • Communication of Sunday attendance should be communicated earlier in the project to allow staff more time to plan ahead
  •  

 