You are viewing an old version of this page. View the current version.
Compare with Current
View Page History
« Previous
Version 15
Next »
Lessons learned notes (IS&T session held 01/28/2011)
Project Organization
- Steering Committee
- - Based on feedback from last years Support Pack Project the Steering Committee was expanded to include more BPO representation.
- - The general consesus was this was a good idea as in prior years BPO representation was inadequate.
- - Should create an email list for committee members.
- Core Team
- - Worked well; representation was adequate.
- - Testing coordinators made organizing work easier.
- - QA representation (a point person) on the team proved beneficial to the QA team and the project as a whole.
- - Transport coordinator continues to play an important role.
Planning/Schedule
- Adequate for the project
- Validation by BPO should be tested before cutover weekend (some testers where not the normal executers or the transactions being tested)
- Remote cutover testers should test connections to system before cutover weekend
Testing
- Unit Testing
- Keep the 5 day unit test window - new functionality has been introduced; the time for testing/resolving issues is needed
- We used an Access db to store a catalog of the transactions we tested by whom and compared to last year
- concept was good and has value
- the execution was rushed (the db was not really "production" ready)
- the tool was a little klugy
- better solution should be explored (within SAP, within SM)
- Should consider storing unit test cases in QC to promote a single consistant cataloging approach
- SIT/UAT Testing
- QC - central repository for catalog of test cases
- Worked well as a catalog for test cases
- Great for monitoring execution status
- Saved preparation time of test "lab" for BAs (cases already in QC and available for use)
- Test cases for the most part were not ready for QC formatting
- Cases are/were designed for printing
- A focused effort updating the cases to be QC formated would be beneficial to the process (requires resources)
-
Transports
- Transport freeze
- Critical transport process
Communication
- Project wiki
- Great for dates and status, assuming it is kept up-to-date
- Was used as reference by all IS&T participants
- Could be used to report cutover status in addition to status phone line, emails, etc ...
- Status line was used by IS&T staff
- Frequency of meetings
- Core Team Monthly meetings - adequate and focused
- Functional BA - daily meetings during testing phases kept teams focused
- Did people feel they knew what was going on and what was expected of them? - Yes
- Other
- Could utilize WebEx - in light of IS&T moves
Cutover
- Communication
- The Plan itself
- emails- Subscribe to email list of core team during the project/during cutover (watcher list could be added)** phone
- conference line - use WebEx to allow more participants on the call
- validation steps
- Execution
- For the most part ran smoothly - went live slightly ahead of schedule
- Cutover plan contained necessary details for successful execution
- Other
- Communication of Sunday attendance should be communicated earlier in the project to allow staff more time to plan ahead
-