The General Contract Change Order process combines previously approved Change Order Requests, generated using the 06.01 Letter or Release/ Change Order Request process, into a Contract Change Order for final approval.
    • This process is usually started by the project manager, however it can be started by the contractor.
    • The process routes the GCCO for approval and signature by the appropriate parties based on dollar amount and program.

    1. Start

    2. PM Review

    3. Initiator Revise

    4. Project Budget Change (Decicional Step)

    5. $0 Change? (Decisional Step)

    6. Spawn $0 Budget Change

    7. Spawn Additional Funding

    8. Time Only? (Decisional Step)

    9. Fin. Analyst Holds for Completion

    10. GC Change Order M.M

    11. Sum of Attached CORs

    12. Success? (Decisional Step)

    13. Commitment Value CO

    14. Success?

    15. GC Change Order M.M. (Mail Merge)

    16. Initiator Resubmit

    17. PM Review Mail Merge

    18. Vendor Signature

    19. Vendor Signature St

    20. A/E Review Required? (Decisional)

    21. A/E Signature

    22. PM Review

    23. Program Manager Review

    24. Program Director Review

    25. <10m? (Decisional Step)

    26. CC Director Executes

    27. CC DIrector Signs

    28. <$100 (Decisional Step)

    29. Deputy EVPT Review

    30. EVPT Executes

    31. CO Signature Finalize

    32. Compl CORs on Hold

    33. Success? (Decisional Step)

    34. eB Admin Resubmit

    35. Finish

    Date Change eB Admin
    4/3/2018 Process updated to enable signaure step for CC Director when value of GCCO is <10 milion. (Workflow v4.1) RB/SA
    4/3/2018 WIKI documention (Step Descriptions and Process map updated) RB