Result or Product of this Process

The purpose of the Project Definition Form Creation process is to create and route a PD Form through an approval system for non-Capital and non-Academic projects.  This process spawns the 03.01 Milestone Project Estimate and Budget Request process.

Process Details

    This process can be started by:

    • CC Planner
    • CC Planning Manager
    • eB Admin
    • Project Manager
    • R&M Manager
    • UTLITIES-Program Manager

    1. Start

    2. CC Planner Created?

    3. CC Planner Completes PD Form

     4. Project Manager Review

    5. Initiator Review

    6. CC Planner Revise

    7. Planning Manager and Prog. Manager Review

    8. Working Committee Review

    9. Utilities, O&M and SEG Review

    10. Create PD Form (Mail Merge Step)

    11. One Funding Source? (Conditional)

    12. Spawn 03.01 Milestone Project Estimate and Budget Request - (COST) (MPEB)

    13. Finish

     

     

     

     