Result or Product of this Process

This process can be initiated by Project Managers and Project Coordinators. This process will also regularly be spawned from the MUS1 process.

Process Details

    • Process to be used to enter a conceptual, schematic design, or design development estimate into the cost module. Costs entered through this process do not effect the budget module and are for estimate purposes only. 
    • Each of these processes can be used to enter estimates that appear in the corresponding Cost module column. An estimate cannot be submitted for approval. To enter a budget and gain approval use the 3.01 process.
    • Using these processes the project manager can:
      • Upload budget estimates without a sequence of approval steps. Whatever is submitted will appear in the Cost module immediately.
      • Ask for input or review of the budget from others by directing them to view the Cost module.
      • Repeatedly upload versions of each estimate and replace the previous estimates.
      • Attach supporting documentation to an estimate.

    Start

    Finish