Role  | Members  | Primary Responsibilities  | Communication  | 
|---|
Sponsors  | Olu Brown, Director, Platform Engagement, IS&T, MIT  | - Provide overall direction, goals & funding
 - Approve charter, scope, milestones, budget
 - Remove obstacles
 
  | - Monthly written status report
 - Invitation to attend steering committee each month
 
  | 
Steering Committee  | 
 Lisa St. Croix, IT Systems Project Manager, Facilities Laurie Veal, Program Manager, EHS Management System, EH&S Kathy McGrath, Director of Financial Operations, VPF Danielle Khoury, Controller, VPF Wayne Turner, Director, HR Technology, HR Olu Brown, Director, Platform Engagement, IS&T, MIT
 
   | - Provide oversight, schedule resources
 - Define roles & responsibilities
 - Set standards, guidelines, processes, metrics
 - Remove obstacles, resolve issues
 - Approve go/no go decision
 
  | - Monthly steering committee meetings - September - January
 - September - 9/19
 - October - TBD
 - November - TBD, Go/No Go decision
 - 1/2018 (TBD) Post project review
 
  | 
Project Manager  | Lori Singer, MIT  | - Complete project on time, on budget
 - Manage overall project: plan, track progress, resolve issues, escalate when necessary, ...
 - Communicate: with project team, sponsors, steering committee, stakeholders, broader community
 - Ensure appropriate business and IS&T resources are assigned to project tasks
 - Coordinate work among project teams, data warehouse, OIS, IS&T help desk, ...
 
  |    | 
Transport Coordinator  | Elda Prudden  | - Define process, lists, tracking procedures
 - Plan and track effort to move pending transports to production before freeze
 - Manage any critical transports during freeze to ensure they are included in upgrade
 - Manage all transports related to support pack project
 
  |    | 
Core Team: Technical Leads  | R3 Administration Team Infrastructure Team Lead - Ron Parker  | - Prepare environments
 - Apply support packs related to support pack project * Execute SF3 modification testing; Resolve & retest issues
 - Unit test (joint with functional team)
 - Analyze & resolve issues
 - Execute cut-over activities
 - Coordinate work of basis team and developers
 
  | - Daily Scrum PO Meetings
 - Kick off meeting 9/26
 - sap-upgrade-core@mit.edu
 - project wiki
 
  | 
Core Team: Functional Leads  | - HRP (HR/Payroll) PO - Frank Quern
 - Benefits
 - Compensation
 - Human Resources (Service Center)
 - Payroll
 - Pension Payroll
 - Enterprise Learning
 
  - FLE (AP/FI/PO) PO - Bob Casey
 - AP
 - Travel
 - Procurement
 - Facilities Financial Reporting
 - FAR
 - Coupa integration
 - SMART (Singapore)
 
  - Facilities (PM/EH&S/Parking Office) PO - Jim Fragala
- EHS
 - Facilities
 - Parking
 
  - Atlas, Automated Testing  - Lisa Robinson
 - System Architect - Olu Brown
 
  | - Unit testing (joint with technical team, track and report process)
 - Coordinate, update and execute automated testing
 - System integration testing (define scope, update & execute scripts, track and report progress)
 - User acceptance testing (assist if needed)
 - Serve as primary liaison with business owners
 - Analyze & resolve issues
 - Execute cutover activities
 - Coordinate work of business analysis and business owners
 - QA
 - Define & communicate process & templates to manage test cases
 - Set standards for quality assurance process
 - Oversee QA work on the project
 
  
  | - Daily Scrum PO Meetings
 - Kick off meeting 9/24
 - sap-upgrade-core@mit.edu
 - project wiki
 
  | 
Extended Team  | - ist-sap@mit.edu 
- which includes all IS&T staff supporting SAP
 - Contact Frank Quern or Bob Casey if you are not on the list and think you should be
 
  
  | - Perform tasks as directed by core team leads
 
  | - Kick off meeting in September, before SAPbiz kickoff
 - ist-sap@mit.edu
 - project wiki
 
  | 
Business Owners  | - FAR, JV - Ross Monaghan
 - HR/Payroll - Chris Durham (Leslie Wright, BA)
 - HR/Benefits - Mike MacDonald, Diane Sullivan
 - Facilities - Lisa St. Croix
 - Stockroom - Tammy Doyle
 - EHS - Laurie Veal, Joe Macleod
 - Spons. Billing - Timothy J Vacha, Dale C Twomey
 - Gen AR - Rachel Arons
 - Cashiers - Rachel Arons
 - Property: Kevin J Milligan, Jo-Anne M Chute
 - Fund Centers: Peggie McGrath
 - IST Telecom: Allan Wallace
 - Tech Review: TBD
 - AP - Joanie Edmonds (Leslie Wright, BA)
 - Procurement - Kathy McGrath (Cindy Vye, BA)
 - Coupa - Kathy McGrath (Cindy Vye, BA)
 - Travel - Kathy McGrath (Cindy Vye, BA)
 - SMART - Clara Ng Ching Ching, Jahan Habib
 - OSP - Sabari Nair
 - OBO - Jason Leung
 - Pcard - Kathy McGrath, Kim Harmon
 - EL - Jane White, Melissa Kavlakli, Mae Jones
 - Merchant Services - Chris Durham, Michael Philbrick
 - Sponsored Accounting - Emily Dimond, Rich Corrente, Long Tran
 - OGE/GAP - Scott Tirrell
 
  | - Perform user acceptance testing (define scope, update & execute scripts, retest as needed)
 - Report issues via email to lsinger@mit.edu
 - Train end users if any changes are discovered (none anticipated)
 - Sign-off that updated system is accepted for your business area and support packs can move to production
 - Perform any business cut-over activities
 - Validate production system (define criteria, validate system)
 
  | - Kick off meeting @  SAPbiz meeting
 - Every other week at SAPBiz or as required
 - Meeting minutes and updates available on this wiki
 - project wiki
 - Weekly HRP Test planning meetings
 
  |