High-Level Timeline
By end-of-day Nov 4 - Plan, create/update test scripts in ALM. (SAP Business Areas)
End of day production snapshot from 9/20/2021 to be used to refresh SF3 and SH1 environments
End of day production snapshot from 10/18/2021 to be used to refresh SH2 environments
Refer to calendar for detailed time frames
2021 SAP Support Pack Upgrade - Calendar View
Nov 30-Dec 3 - Uptime Production Cut-over Activities -
Dec 3-Dec 5 - Go-live weekend! (start Friday at 5pm)
Dec 6 - Upgraded PS1 is ready for use
---------
SAP Scheduled Upgrades - Ancillary Systems
ERP Target
ERP:
GRC:
NetWeaver/ADS:
SAP Mobile: