High-Level Timeline

By end-of-day Nov 4 - Plan, create/update test scripts in ALM. (SAP Business Areas)
End of day production snapshot from 9/20/2021 to be used to refresh SF3 and SH1 environments
End of day production snapshot from 10/18/2021 to be used to refresh SH2 environments

Refer to calendar for detailed time frames

2021 SAP Support Pack Upgrade - Calendar View

Nov 30-Dec 3 - Uptime Production Cut-over Activities -

Dec 3-Dec 5 - Go-live weekend! (start Friday at 5pm)

Dec 6 - Upgraded  PS1 is ready for use

---------

SAP Scheduled Upgrades - Ancillary Systems
ERP Target

 

 

 

ERP:

 

 

GRC:

 

 

NetWeaver/ADS:

 

 

SAP Mobile:




 