The following is a copy of the Support Pack Cut-over and Test Plans:
2023 SAP Support Pack Cutover Plan
2023 FLE Validations
2023 HRP PS1 Business Validations.xlsx
2023 PS1 User List
2023 Final Post Upgrade Transport List
Communication
Project cutover status of the upgrade, see below, will be posted on this wiki page beginning at noon on Friday 12/1/2023 through noon on Monday 12/4/2023. The Project Manager will update this message as needed. A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.
Project Status:
Sunday 12/3/2023 7:30AM: On Track. Business Team Validations are set to begin SUNDAY/today at 10:30AM
|
|---|
Conference Calls (Zoom) for cut-over weekend:
Saturday 4:30PM IS&T
Sunday 1PM Validation review
Error rendering macro 'viewxls'
com.atlassian.confluence.macro.MacroExecutionException: com.atlassian.confluence.macro.MacroExecutionException: The viewfile macro is unable to locate the attachment "2023 SP - Cutover Plan.xlsx" on this page