  • CADed a chassis for the payload
    • 7.5in Cube
    • 2 layers split by a divider plate
    • Balloon's 4 point harness attached to base plate, no top plate. Initially planned on mounting to a roof fixture, but changed to floor fixture because: a) it'd be redundant to have both a roof for the chassis and a roof of foam, and b) it'd make it hard to move things around and physically insert things.
  • Improvements to be made 
    • Fix up timing next time and make sure to properly train everyone in CADing so a last minute grind doesn't need to be done again, and so that we have time to test, and play around with the physical model prior to launch
    • Get a better visual idea of how to budget space (i.e. allocating better clearance)
  • Other Ideas
    • Solid wall box
    • 3 Layers
  • Cut Foam for temperature insulation
    • Everything was measured precisely and cut out in accordance



  • No labels