Key Dates
Support Pack Project
- Now - October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
- 10/18/2010 - End of day production snapshot to be used to refresh test environments
- 11/01/2010 - Development Freeze begins
- 11/10/2010 - Last date to implement support & enhancement changes until freeze ends on 12/15/2010
- 11/04/2010 - 11/10/2010 Unit test
- 11/11/2010 - 12/10/2010 System Integration Test
- 12/10/2010 - 12/12/2010 Go-live week end
- 12/15/2010 - Development Freeze ends