1. By Sunday, 11/27/2011 8 AM Download Basis notes for the PS1 required for the upgrade
2. Sunday, 11/27/2011, 8 AM DSM Upgrade & associated notes.
3. Sunday, 11/27/2011 10 AM Begin online upgrade piece of the application of Enhancement Pack(s)
4. Monday, 11/28/2011, by 9 AM Post messages on insideMIT, SAPweb and ESS Web sites of upcoming SAP outage.
5. Monday 11/28/2011, 12 PM* Send message to MIT-SAP community about upcoming SAP outage.
6. Monday, 11/28/2011, 12 PM Post message on SAPgui indicating upcoming SAP outage.
7. Tuesday, 11/29/2011, 10:30 AM IS&T - Cutover weekend planning meeting.
8. Wednesday, 11/30/2011, 10 AM-12 PM SAP upgrade Core/Action log team meeting - review Cutover schedule and details.
9. Thursday, 12/1/2011. 12 PM Steering Committee Meeting - review cutover plan.
10. Thursday, 12/1/2011, 1 PM Email Steering Committee Go/No-go decision.
11. Thursday, 12/1/2011, 2-3 PM Final review - RT issues, transport list, web components.
12. Thursday, 12/1/2011, By 4 PM Schedule Pre & Post Trail balance reports.
13. Thursday, 12/1/2011, By 4 PM R3-Admin email nessage about system down time.
14. Thursday, 12/1/2011, By 4 PM Final copy of Production Update Schedule published and emailed.
15. Friday, 12/2/2011, By 12 PM (Noon) Facility Supervisors print out work lists as back up for Monday morning.
16. Friday, 12/2/2011, By 12 PM (Noon) Reschedule (shift) DW batch jobs to Sunday night.
17. Friday, 12/2/2011, By 4:30 PM Suspend weekend MITSIS Grad Appointment feed.
18. Shift Concur outbound jog to 4:30pm
19. Friday, 12/2/2011, By 5:00 PM Workflow and JV Validation Reports.
20. Friday, 12/2/2011, 4:35 PM Stop EDI Production Jobs.
21. Friday, 12/2/2011, 5 PM Shut down EDI application server.
22. Friday, 12/2/2011, 5 PM Voice message update when system goes down.
23. Friday, 12/2/2011, 5 PM System Downtime Message (3-Down)
24. Friday, 12/2/2011, 5 PM Bring down application servers. Production Environment becomes unavailable.
25. Friday, 12/2/2011, 5 PM Disable Gateways.
26. Friday, 12/2/2011, 5 PM Suspend Drop-box processing.
27. Friday, 12/2/2011, 5-7 PM Validation Reports (Trial Balance) executed in SAP.
28. Friday, 12/2/2011, 5-7 PM Limited activity in PS1.
29. Friday, 12/2/2011, 7-10 PM Backup PS1.
30. Friday, 12/2/2011 - Saturday, 12/3/2011, 10 PM - 12 PM (Noon) SAP ERP: Execute support pack application.
31. Saturday, 12/3/2011, 1-5 PM Backup System.
32. Saturday, 12/3/2011, By 3 PM Upgraded GuiXT scripts moved to Facilities Production Server.
33. Saturday, 12/3/2011, 4 PM Conference Call Check-in - use webex line.
34. Saturday, 12/3/2011, 5-10 PM Execute Oracle DB Upgrade.
35. Saturday, 12/3/2011 - Sunday, 12/4/2011, 10 PM - 2 AM Backup System.
36. Saturday, 12/3/2011 - Sunday,12/4/2011, 10 PM - 8 AM Generate DB Statistics; Complete ABAP loads.
37. Sunday, 12/4/2011, 3-5 AM Transports Application.
38. Sunday, 12/4/2011, 8 AM Validation reports executed (trial balance reports).
39. Sunday, 12/4/2011, 10 AM Unlock web-services ids in Production.
40. Sunday, 12/4/2011, By 11 AM Enable Gateways (SAPWeb/ESS).
41. Sunday, 12/4/2011, By 11 AM EDI Step 1: Update SAP EDI Version number.
42. Sunday, 12/4/2011, By 11 AM EDI Step 2: Turn on the EDI 'gourmet-1' server.
43. Sunday, 12/4/2011, By 11 AM EDI Step 3: Schedule EDI job.
44. Sunday, 12/4/2011, By 11 AM Email to ist-sap@mit.edu.
45. Sunday, 12/4/2011, 11 AM R3-Admin Action Log.
46. Sunday, 12/4/2011, 12 PM - 2 PM ADMIN SYS Action log tasks.
47. Sunday, 12/4/2011, By 2 PM Update voice message whether Data Validation is on schedule.
48. Sunday, 12/4/2011, By 2 PM Unlock testers.
49. Sunday, 12/4/2011, 2-4 PM PS1 Data Validations & Transaction processing.
50. Sunday, 12/4/2011, By 4 PM Coordinators for each area should send email to sap-validation-team@mit.edu at the completion of the validation notifying results.
51. Sunday, 12/4/2011, 4 PM Conference Call Check-in Go/No-Go decision - use webex line.
52. Sunday, 12/4/2011, after conference call send email notifying results.
53. Sunday, 12/4/2011, 8 PM - 12 AM Data Warehouse Job Validation.
54. Sunday, 12/4/2011, 8-10 PM Unlock users.
55. Sunday, 12/4/2011, 10 PM Enable Dropbox.
56. Sunday, 12/4/2011, 10 PM Execute ProCard from Bank of America feed.
57. Monday, 12/5/2011, 1:30 AM On Line back up of PS1.
58. Monday, 12/5/2011, By 6AM Update 3-down web page & SAPgui message.
59. Monday, 12/5/2011, By 6 AM Remove SAPweb, ESS and EHS messages.
60. Monday, 12/5/2011, 6 AM Email notification to MIT community stating update complete and production available.
61. Monday, 12/5/2011, 9 AM Reinstate weekend MITSIS Grad Appointment feed.