Cut-over Plan Progress:
57%

SP Preparation Tasks and Processes (11/26 - 11/30)

  1. handler

    1. Monday by 9am - Post messages on insideMIT, SAPweb and ESS (Employee Self Service) web sites about upcoming SAP outage.

    Priority MEDIUM
    fquern@mit.edu
    Nov 26, 2012 23:57
  2. handler

    2. Monday by 10am - Post message on ECAT web site about upcoming SAP outage.

    Priority MEDIUM
    fquern@mit.edu
    Nov 27, 2012 00:00
  3. handler

    3. Monday 10am - Begin online upgrade piece of the application of Enhancement Pack(s)

    Priority MEDIUM
    fquern@mit.edu
    Nov 27, 2012 00:01
  4. handler

    4. Monday 12pm - Post message on SAPgui indicating upcoming SAP outage

    Priority MEDIUM
    fquern@mit.edu
    Nov 27, 2012 00:06
  5. handler

    5. Monday by 5pm - Confirm that there are no GuiXT Changes

    Priority MEDIUM
    fquern@mit.edu
    Nov 27, 2012 00:08
  6. handler

    6. Monday by 5pm - Send message to MIT-SAP community about upcoming SAP outage.

    Priority MEDIUM
    fquern@mit.edu
    Nov 27, 2012 00:09
  7. handler

    7. Tuesday 10:30am - Cutover weekend planning meeting IS&T.

    Priority MEDIUM
    fquern@mit.edu
    Nov 27, 2012 00:15
  8. handler

    8. Tuesday 12pm - Steering Committee Meeting – review cut-over plan/ Go/No-go decision – W92

    Priority MEDIUM
    fquern@mit.edu
    Nov 27, 2012 00:16
  9. handler

    9. Tuesday by 5pm - Email Steering Committee Go/No-go decision

    Priority MEDIUM
    fquern@mit.edu
    Nov 27, 2012 00:18
  10. handler

    10. Wednesday 10:30am - 12pm - SAPbiz meeting to review the Production Cutover schedule and details, including action log and user support

    Priority MEDIUM
    donovan@mit.edu
    Nov 29, 2012 10:15
  11. handler

    11. Wednesday 2:00 - 3:00pm - Final review all issues in RT project queue, transport list, and web components.

    Priority MEDIUM
    donovan@mit.edu
    Nov 29, 2012 10:16
  12. handler

    12. Wednesday 3:00 - 4:00pm - SAP Action log team meeting to review the Production Cutover action log.

    Priority MEDIUM
    donovan@mit.edu
    Nov 29, 2012 10:17
  13. handler

    13. Wednesday by EOD - Final Copy of the Production Update Schedule published and emailed.

    Priority MEDIUM
    donovan@mit.edu
    Nov 29, 2012 10:18
  14. handler

    14. Wednesday by EOD - R3-Admin email message about system down time

    Priority MEDIUM
    donovan@mit.edu
    Nov 29, 2012 10:18
  • No labels