BMC has agreed to the following next steps in terms of amendments to the draft SOW (attached) to be delivered by 2/20:

  • Upgrade the current Dev environment to Remedy 2013.1 and use this to build the prototype
  • Increase RAM as need to improve performance for both the Dev and QA environments
  • Including Analytics to build prototype reports (see use case 3)
  • 3 payment milestones to correspond to completion and approval of deliverables for each phase:
  • Remedy OnDemand Live! Prep
  • Service Request Management
  • Solution Enhancement
  • Estimated start date of March 18th
  • Target completion date of May 24th
  • Statement as to how this initiative will reduce the costs of a future implementation effort
  • One addition we did not discuss today but require:a bio or CV for each of the professional services staff that will be working on this engagement

MIT IS&T has agreed to the following next steps:

  • Pat and Chris will identify and engage with needed stakeholders and subject matter experts that will be involved in this effort by mid March