High-Level Timeline


Now thru the end of October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
(tick) 10/10/2013 – SAP release of year end base level support pack
(info) 10/21/2013 - End of day production snapshot to be used to refresh test environments
(info) 10/19/2013 - Development Freeze begins
(info) 10/31/2013 - Last date to implement support & enhancement changes until freeze ends on 12/11/2013
(info) 10/25/2013 - 11/01/2013 Unit test

(info) 11/04/2013 - 12/01/2013 System Integration Test (regression test fixes: 11/26-27 & 12/1)

(info) 12/7/2013 - 12/8/2013 Go-live weekend!

(info) 12/11/2013 - Development Freeze ends