Project Timelines and Milestones:

  • Goal is to roll out HR Staffing Services web site by early fall

Revised timeline and major milestones for the NEO web site project:

  • 4/11 RFP distributed
  • 4/23 Vendors Selected
  • 5/1 Kickoff Meeting
  • 9/3 Target Release Date

Consolidated Design and Writing Schedule (updated 6/09/08)

Development Schedule (updated 7/01/08)

Multimedia Development Schedule (updated 6/09/08)