Updated 6/09/08
N.B. This is a proposed schedule; not all events have been confirmed.
 Date   | 
 Description   | 
 Contact   | 
 Comments   | 
|
 6/11/08   | 
   Intro draft script   | 
 Kath T-L   | 
 To Julienne & Janet; establish the correct tone and approach   | 
|
 6/11/08   | 
 Detailed Topic list   | 
 Ken   | 
 To Kath T-L. Need to identify topics 1-7 and 8-14, along with missing content.   | 
|
 6/13/08   | 
 Feedback on intro draft script   | 
 Janet   | 
 To Kath T-L. Little or no benefits vetting required   | 
|
 6/13/08   | 
 Email announcement- NEO Idol Auditions   | 
 Julienne   | 
 To H-R staff. Requesting volunteers to audition for the multimedia voiceovers. Need confirmed audition dates and times.   | 
|
 6/24/08   | 
 Topics 1-7 drafts   | 
 Kath T-L   | 
 To Julienne & Janet   | 
|
 6/24/08 &   | 
 Audio auditions   | 
 Ken   | 
 Time TBD. Two 1 hour sessions.   | 
|
 7/1/08   | 
 Identify audio performers   | 
 Julienne   | 
 Strong input from MIT AV expected. Also, identify which topics will be read by which performers.   | 
|
 7/1/08   | 
 Feed back on topics 1-7 drafts   | 
 Janet   | 
 To Kath T-L; requires vetting by Benefits   | 
|
 7/1/08   | 
 Topics 8-14 drafts   | 
 Kath T-L   | 
 To Julienne & Janet   | 
|
 7/1/08   | 
 PowerPoint templates   | 
 Wing   | 
 To Ken.   | 
|
 7/8/08   | 
 Feed back on topics   | 
 Janet   | 
 To Kath T-L; requires vetting by Benefits   | 
|
 7/8/08   | 
 Topics 1-7 final drafts   | 
 Kath T-L   | 
 To Julienne & Janet   | 
|
 7/15/08   | 
 Topics 8-14 final drafts   | 
 Kath T-L   | 
 To Julienne & Janet   | 
|
 7/15/08   | 
 Final Multimedia topic sequence   | 
 Janet   | 
 To Ken. This is the order in which topics will play in the Flash viewer; aka a table of contents   | 
|
 7/22/08   | 
 First Flash build   | 
 Ken   | 
 To the team. Will lack audio (or may have a raw recording)   | 
|
 7/23/08 pm   | 
 Audio Recordings   | 
 Ken   | 
 @MIT AV. Kath T-L to be present for last minute rewrites   | 
|
 7/25/08   | 
 Feedback on first Flash build   | 
 Ken   | 
 From the team.   | 
|
 7/29/08   | 
 Second Flash build   | 
 Ken   | 
 To the team. Will contain audio recordings   | 
|
 8/12/09   | 
 Feedback on second Flash build   | 
 Ken   | 
 From the team.   | 
|
 8/15/08   | 
 Post Final build for QA   | 
 Ken   | 
 To Laurie   | 
  |