Overview

Supplies were organized in lab according to the Hermes II Launch Packing List on Thursday evening by Charlie G. Megan C. Vittorio C. Dennis G. and Jakob C. As packing checklists were completed supplies were moved downstairs to the lobby. Early on the morning of the 14th a car was rented, packed and departed at approximately noon driven by Megan and Vittorio. It is expected to arrive in Los Angeles on Monday evening.

Action Items

Packing revealed the following action items

  • Packing status of sustainer Marsa is unknown
  • We are out of RTV silicone - none shipped
  • Waterjet broken - in the future we should NOT plan to waterjet parts the morning of... just saying
    • Booster forward insulation incomplete
    • Booster nozzle insulation
    • Sustainer forward closure
  • Epoxy and Proline not shipped
  • Sowing machine broke during critical path manufacturing
    • Booster chute incomplete
    • Booster sleeve incomplete
    • Sustainer drogue sleeve
    • Sustainer drogue bag
    • Sustainer Drogue
    • Sustainer Main
  • Staging demo t-fittings not yet ordered
  • Staging demo fasteners not ordered
  • Radio Beacons: 2 good ones shipped. One broken unit with Dennis G. for repair
  • Payload Stack deemed undready for integration. Shipping list not performed. No parts shipped
  • Avionics Packing List Item 'Ground Station Box' was not known and could not be located. Attempts to contact avionics personnel failed. May or may not have shipped
  • Ground Station Pyxidas not shipped
  • Lower Electronics deemed undready for integration. Shipping list not performed. Some parts shipped integrated with FRR.
  • All blue dentists tools used for clocking alignment are broken. None shipped- ordered 6/20/19 and will bring with me to launch- Maggie

Attached are signed copies of the packing sheets. These have been included in a binder shipped with the vehicle. Items in esoteric locations have their box noted on their packing sheet.

Photos.zip

  • No labels