Resources needed for rapid analysis of W events from 2009 pp 500 GeV run
(relay only RCF resources)
Updated 16 April 2009 (UTC)
Primary goal is publication of W xsection. Approaching conferences do not define deadlines for intermediate results.
We will work first on sufficient quality calibration.
If final TPC tracking accuracy is not adequate we will not publish separately W+ vs. W- .
- real events data sets , obtained ~1TB (mit+iucf+data05+06+07)
- 1.1M L2W tagged events saved in W-stream (muDst=400GB)
- 1.5M VPD minB events from Fill F10471 (muDst=500GB)
- MC events Pythia 500 GeV, geometry 2009, needs ~200GB (uky)
- 1M filtered QCD Pythia events partPT>10 GeV/c, LT=10/pb,filter: stable particle 'cluster' ET>20 GeV, 5e8 Pythia events thrown
- assorted rare Pythia events involving Ws, Zs, W-jets, etc, above 100/pb apiece
- TPC calibration needs : low lumi data set at 200 GeV 3M events (to be taken!) , 200GB disk for muDst (data07), 1-2 CPU years
- status tables (time) , per longer runs
- TPC: variety of corrections based on low lumi run (to be taken at pp 200 GeV) and sampled pp 500 data
- twist, inner/outer alignment done by STAR core team - 1 week of work according to Gene
- Space Charge corrections by Joe: muDst=200GB, 2.5 CPU month per pass, 3-8x iterations
- TPC: evaluation of achieved pT resolution - 1 week
- determine beam line constraint
- Vertex finder QA - 1 week
- EMC calibrations: ~week of CPU , few weeks of FTE per detector
- QA of runs
- status tables (BTOW,ETOW,BSMD) , pedestals (BTOW,ETOW), per fill
- BTOW: relative gains (per towers) from slopes from minB eve, absolute=ideal
- ETOW: as above
- BSMD: relative gains (per strips) from slopes from minB eve , absolute using 2008 pp calibration (done)
- polarization related: STAR bXing, fill pattern, CNI : fill pol(time)
- BPRS, TOF - not used unless needed
- CPU needs for data analysis: 2 CPU years (TPC calibration effort not included)
- full BFC production of L2W events: (28sec/eve), 250 CPU days per pass (assume 2nd iteration may be needed)
- real muDst analysis: 13 Hz, 1 CPU day/pass, x 20 iterations
- MC muDst analysis: 13 Hz, 1 CPU day/pass, x 20 iterations
Approximate schedule, milestones, an estimate
- calibrations ~1-2 months
- BFC 1st production ~1 week
- tuning of W-cuts ~2 weeks, first W peak in ET spectrum
- comparison to M-C, efficiency : ~1 month
- (if needed) BFC 2nd production : ~1 week
- final analysis , preliminary cross section released : ~1 month
- writing paper, cleanup of analysis, draft ready for spin PWG : ~3 months
- comments from spin PWG, analysis : ~2 months, draft ready for GPC
- working w/ GPC : ~3 months, paper sent to publisher