The high-level schedule is:

Aug 2007: pilot for Stellar, Thalia, Confluence, MAP packages available

Jan 2008: evaluate pilot, new development as needed

May 2008: development ends, testing begins 

Aug 2008: production to MIT community 

The following represents various detailed steps along the way. These are being re-worked into a single detailed schedule, with dates, indivduals responsible, dependencies, and hand-offs.

WebSSO Milestones
WebSSO Prototyping
WebSSO Pilot