Q3 -- awaiting content

IS&T Publishing Group
2009 Q3 Publishing Group Summary
Mark Wiklund
 Accomplishments

  • In Q3 2009, the IS&T Publishing Team was actively engaged on multiple projects originating from all areas of IS&T. We produced and published documentation supporting MS Exchange Email & Calendaring, PGP, Fall Readiness 2009, and other software and service releases. 
  • During Q3, the Web Production team reviewed and published a 171 new pages to the IS&T website, 374 updates to existing pages, and archived 1,217 pages containing information deemed obsolete.  
  • The IS&T Publishing Team, in concert with ISDA, is on schedule to go live with the redesigned IS&T website on July 1. Accomplishments in Q3 include:
    • Pre-migration clean-up of current IS&T content
    • QA and go-live strategies implemented

 Challenges for Q4
 

  • Complete and publish user documentation required to support the Exchange Email/Calendaring implementation.
  • Complete the QA, and User Acceptance of content migrated into the redesigned IS&T website.
  • Define and implement new Publishing policies for the IS&T Website and Drupal CMS
  • Manage content freeze effectively during migration

   

...

Q2 -- already submitted


Wiki Markup
\[ 1/16/2009 \]

...