Key dates

  • Now - October - Plan, improve test scripts
  • 10/05/2009 - Last date to implement projects until freeze ends on 12/24/2009
  • 10/22/2009 - Last date to implement support & enhancement changes until freeze ends on 12/24/2009
  • 11/16/2009 - 11/29/2009 System Integration Test
  • 11/30/2009 - 12/09/2009 User Acceptance Test
  • 12/11/2009 - 12/13/2009 Golive Weekend
  • 12/24/2009   Freeze ends 

...