Month

Major Deliverables

Responsible

August

  1. Plan, resources, kickoff
  2. QA instructions, templates
  3. Test scope defined
  4. Consolidated master test catalog
  1. Bart
  2. Wendy
  3. Core Team - Functional / Wendy
  4. Core Team - Functional

September

  1. Pending work moved to production
  2. Updated test scripts
  1. Core Team - Functional
  2. Core Team - Functional

October

  1. System preparation
  1. Core Team - Technical

November

  1. Unit Test
  2. System Integration Test
  1. Core Team - Technical/Functional
  2. Core Team - Functional

December

  1. User Acceptance Test
  2. Production
  1.  Business Owners
  2. All

Current Detail Plan

TBD - process, environment, plan to allow project work development and testing to move through landscape immediately following support pack work.