October 7, 2009 Steering Committee 9-10am W92-240 Riverside
Agenda:#
- Some Lessons Learned from 2008
- Project wiki
- Freeze date confusion
- Project go-lives too close to freeze dates
- Test scripts
- Roles, teams
- Progress to date:
- Budget
- This year's project IS&T Budget 3500 hours; $240K. Actuals thru September not complete.
- Last year's project IS&T Actual 3105 hours
- Increase in this year's hours to continue test script updating, organizing.
- Risks & issues
- Other
- Next meeting - November 4, 2009 9-10am W92-240 Riverside