|| Role || Members \\ || Primary Responsibilities || Communication ||
| Sponsor | Christine Meholic | * Provide overall direction, goals & funding
* Approve charter, scope, milestones, budget
* Remove obstacles | * Monthly written status report
* Invitation to attend steering committee 1st Monday each month |
| Steering Committee \\ | # Bart Dahlstrom
# Wendy Bastos
# Kevin Lyons
# Ken Levie
# Gillian Emmons | * Provide oversight, schedule resources
* Define roles & responsibilities
* Set standards, guidelines, processes, metrics
* Remove obstacles, resolve issues
* Approve go/no go decision | * Monthly steering committee meetings - October - January
* 10/5/2009 (Tentative)
* 11/2/2009 (Tentative)
* 12/7/2009 (Tentative)
* 1/7/2010 (Tentative) |
| Project Manager \\ | Ken Levie | * Complete project on time, on budget
* Manage overall project: plan, track progress, resolve issues, escalate when necessary, ...
* Communicate: with project team, sponsors, steering committee, stakeholders, broader community
* Ensure appropriate business and IS&T resources are assigned to project tasks
* Coordinate work among project teams, data warehouse, OIS, IS&T help desk, ... | |
| Transport Manager \\ | TBD | * Manage all transports | |
| Core Team: Technical Leads \\ | # Basis/security - Ron Parker
# ABAP, ITS - Wai-Ming Li
# Web - Rich Murphy | * Prepare environments
* Apply support packs
* Execute SF3 modification testing; Resolve & retest issues
* Unit test (joint with functional team)
* Analyze & resolve issues
* Execute cutover activities
* Coordinate work of basis team and developers | * Weekly core team meeting - Monday 9:30-10:00 W92-North Station starting 8/31/2009
* Kick off meeting 8/20/2009 3-4pm
* sap-upgrade-core@mit.edu
* wiki: [

...

Role

...

Members

...

Primary Responsibilities

...

Communication

...

Sponsor

...

Christine Meholic

...

  • Provide overall direction, goals & funding
  • Approve charter, scope, milestones, budget
  • Remove obstacles

...

  • Monthly written status report
  • Invitation to attend steering committee 1st Monday each month

...

Steering Committee

...

  1. Bart Dahlstrom
  2. Wendy Bastos
  3. Kevin Lyons
  4. Ken Levie
  5. Gillian Emmons

...

  • Provide oversight, schedule resources
  • Define roles & responsibilities
  • Set standards, guidelines, processes, metrics
  • Remove obstacles, resolve issues
  • Approve go/no go decision

...

  • Monthly steering committee meetings - October - January
  • 10/5/2009 (Tentative)
  • 11/2/2009 (Tentative)
  • 12/7/2009 (Tentative)
  • 1/7/2010 (Tentative)

...

Project Manager

...

Ken Levie

...

  • Complete project on time, on budget
  • Manage overall project: plan, track progress, resolve issues, escalate when necessary, ...
  • Communicate: with project team, sponsors, steering committee, stakeholders, broader community
  • Ensure appropriate business and IS&T resources are assigned to project tasks
  • Coordinate work among project teams, data warehouse, OIS, IS&T help desk, ...

...

 

...

Transport Manager

...

TBD

...

  • Manage all transports

...

 

...

Core Team: Technical Leads

...

  1. Basis/security - Ron Parker
  2. ABAP, ITS - Wai-Ming Li
  3. Web - Rich Murphy

...

  • Prepare environments
  • Apply support packs
  • Execute SF3 modification testing; Resolve & retest issues
  • Unit test (joint with functional team)
  • Analyze & resolve issues
  • Execute cutover activities
  • Coordinate work of basis team and developers

...

https://ssit-docs.mit.edu/display/sapscripts/2009+Year+End+SAP+Support+Pack+Project

...

] |
| Core Team: Functional

...

 Leads \\ | # HR/Payroll - Frank Quern

...


# Financial - Mary Ellen Gearin

...


# EHS, Travel \-Lee Collier

...


# Procurement (xECAT3), Facilities, Parking - Rita Zhovnirovsky -

...


# ECAT3 - Elda Prudden

...


# AP, Smart - Ken Levie

...


# Functional Team leads - Julie Block, Bob Romanowicz, Hao Wen

...

 | * Unit testing (joint with technical team, track and report process)

...


* System integration testing (define scope, update & execute scripts, track and report progress)

...


* User acceptance testing (assist if needed)

...


* Serve as primary liaison with business owners

...


* Analyze & resolve issues

...


* Execute cutover activities

...


* Coordinate work of business analysis and business owners

...

 | * Weekly core team meeting - Monday 9:30-10:00 W92-North Station starting 8/31/2009

...


* Kick off meeting 8/20/2009 3-4pm tentative

...


* sap-upgrade-core@mit.edu

...


* wiki: [https://ssit-docs.mit.edu/display/sapscripts/2009+Year+End+SAP+Support+Pack+Project

...

] |
| Core Team:

...

  1. Wendy Bastos
  2. Amanda Gilbert

...

  • Define & communicate process & templates to manage test cases
  • Set standards for quality assurance process
  • Oversee QA work on the project

...

 QA \\ | # Wendy Bastos
# Amanda Gilbert | * Define & communicate process & templates to manage test cases
* Set standards for quality assurance process
* Oversee QA work on the project | * Weekly core team meeting - Monday 9:30-10:00 W92-North Station starting 8/31/2009

...


* Kick off meeting 8/20/2009 3-4pm tentative

...


* sap-upgrade-core@mit.edu

...


* wiki: [https://ssit-docs.mit.edu/display/sapscripts/2009+Year+End+SAP+Support+Pack+Project

...

Extended Team

...

  • All SAIS staff supporting administrative systems
  • ISDA Data Warehouse staff

...

  • Perform tasks as directed by core team leads

...

] |
| Extended Team \\ | * All SAIS staff supporting administrative systems
* ISDA Data Warehouse staff | * Perform tasks as directed by core team leads | * Kick off meeting in September, before SAPbiz kickoff
* sap-upgrade-extended@mit.edu

...


* wiki: [https://ssit-docs.mit.edu/display/sapscripts/2009+Year+End+SAP+Support+Pack+Project

...

Business Owners

  1. GL Reporting, JV - Magdalene Lee
  2. HR/Payroll - Scott Ball
  3. HR/Benefits - Judy Raymond
  4. Facilities - Lisa St. Croix
  5. Stockroom - Tammy Doyle
  6. EHS - Laurie Veal
  7. Spons. Billing - Doug Levie
  8. Gen AR - Jean Roberge/Sue St. Croix
  9. AP - John Larkin
  10. Procurement - Mary Bacci, John Doyle
  11. eCAT - John Doyle
  12. Travel - John Doyle
  13. SMART - Mary Bacci, John Larkin
  14. OSP - Steve Dowdy
  15. OBO - Rob Slauzis

...

  • Perform user acceptance testing (define scope, update & execute scripts, retest as needed)
  • Report issues via RT
  • Train end users if any changes are discovered (none anticipated)
  • Sign-off that updated system is accepted for your business area and support packs can move to production
  • Perform any business cut-over activities
  • Validate production system (define criteria, validate system)

...

] |
| Business Owners \\ | \\
# GL Reporting, JV - Magdalene Lee
# HR/Payroll - Scott Ball
# HR/Benefits - Judy Raymond
# Facilities - Lisa St. Croix
# Stockroom - Tammy Doyle
# EHS - Laurie Veal
# Spons. Billing - Doug Levie
# Gen AR - Jean Roberge/Sue St. Croix
# AP - John Larkin
# Procurement - Mary Bacci, John Doyle
# eCAT - John Doyle
# Travel - John Doyle, <!--  /* Font Definitions */  @font-face 	{font-family:"Cambria Math"; 	panose-1:2 4 5 3 5 4 6 3 2 4; 	mso-font-charset:0; 	mso-generic-font-family:roman; 	mso-font-pitch:variable; 	mso-font-signature:-1610611985 1107304683 0 0 159 0;} @font-face 	{font-family:Calibri; 	panose-1:2 15 5 2 2 2 4 3 2 4; 	mso-font-charset:0; 	mso-generic-font-family:swiss; 	mso-font-pitch:variable; 	mso-font-signature:-1610611985 1073750139 0 0 159 0;}  /* Style Definitions */  p.MsoNormal, li.MsoNormal, div.MsoNormal 	{mso-style-unhide:no; 	mso-style-qformat:yes; 	mso-style-parent:""; 	margin:0in; 	margin-bottom:.0001pt; 	mso-pagination:widow-orphan; 	font-size:11.0pt; 	font-family:"Calibri","sans-serif"; 	mso-ascii-font-family:Calibri; 	mso-ascii-theme-font:minor-latin; 	mso-fareast-font-family:Calibri; 	mso-fareast-theme-font:minor-latin; 	mso-hansi-font-family:Calibri; 	mso-hansi-theme-font:minor-latin; 	mso-bidi-font-family:"Times New Roman"; 	mso-bidi-theme-font:minor-bidi;} .MsoChpDefault 	{mso-style-type:export-only; 	mso-default-props:yes; 	mso-ascii-font-family:Calibri; 	mso-ascii-theme-font:minor-latin; 	mso-fareast-font-family:Calibri; 	mso-fareast-theme-font:minor-latin; 	mso-hansi-font-family:Calibri; 	mso-hansi-theme-font:minor-latin; 	mso-bidi-font-family:"Times New Roman"; 	mso-bidi-theme-font:minor-bidi;} @page Section1 	{size:8.5in 11.0in; 	margin:1.0in 1.0in 1.0in 1.0in; 	mso-header-margin:.5in; 	mso-footer-margin:.5in; 	mso-paper-source:0;} div.Section1 	{page:Section1;} -->Paul Arsenault
# SMART - Mary Bacci, John Larkin
# OSP - Steve Dowdy
# OBO - Rob Slauzis | * Perform user acceptance testing (define scope, update & execute scripts, retest as needed)
* Report issues via RT
* Train end users if any changes are discovered (none anticipated)
* Sign-off that updated system is accepted for your business area and support packs can move to production
* Perform any business cut-over activities
* Validate production system (define criteria, validate system) | * Kick off meeting @ 9/23/2009 SAPbiz meeting
* Every other week at SAPBiz or as required
* Meeting minutes and updates available on this wiki
* wiki: [https://ssit-docs.mit.edu/display/sapscripts/2009+Year+End+SAP+Support+Pack+Project] |