  • Packing status of sustainer Marsa is unknown
  • We are out of RTV silicone - none shipped
  • Waterjet broken - in the future we should NOT plan to waterjet parts the morning of... just saying
    • Booster forward insulation incomplete
    • Booster nozzle insulation
    • Sustainer forward closure
  • Epoxy and Proline not shipped due to large quantity and spillage concerns
  • Sowing machine broke during critical path manufacturing
    • Booster chute incomplete
    • Booster sleeve incomplete
    • Sustainer drogue sleeve
    • Sustainer drogue bag
    • Sustainer Drogue
    • Sustainer Main
  • Staging demo t-fittings not yet ordered
  • Staging demo fasteners not ordered
  • Radio Beacons: 2 good ones shipped. One broken unit with Dennis G. for repair
  • Payload Stack deemed undready for integration. Shipping list not performed. No parts shipped
  • Avionics Packing List Item 'Ground Station Box' was not known and could not be located. Attempts to contact avionics personnel failed. May or may not have shipped
  • Ground Station Pyxidas not shipped
  • Lower Electronics deemed undready for integration. Shipping list not performed. Some parts shipped integrated with FRR.
  • All blue dentists tools used for clocking alignment are broken. None shipped- ordered 6/20/19 and will bring with me to launch- Maggie

Attached are signed copies of the packing sheets. These have been included in a binder shipped with the vehicle. Items in esoteric locations have their box noted on their packing sheet.

...