- Definition of Enhance Packs
- SAP's new approach to delivering new or enhanced functionality. Formerly included in support packs.
- Rationale for including Enhancement Packs in this year's support pack project scope
- Avoid a separate project to add these enhancement packs
- $240K IS&T effort
- Production freeze
- Business testing, validation
- Production outage
- Production validation
- Literally a repeat of the support pack project
- Enhancement packs are a pre-requisite to new functionality
- Required for Enterprise Learning Product - project sponsored by Training Alignment Team, HR, and approved by ASPCC
- Required for other, newer SAP functionality that will be considered as part of 'Administrative System Roadmap'Details
- See attachments for details of enhancement pack content for selected areas of potential interest to MIT. Full list is available here Support Documents.
- MIT Lincoln Lab and other higher ed & research SAP customers following the same strategy
- Approach recommended by project team, approved by sponsor and steering committee.
- Risks & Mitigation
- Enhancement Packs create problems with existing functionality used by MIT
- Don't use Enhancement pack functionality until after year-end support pack project complete
- Test all critical functions as part of the support pack project
- Low probability since we don't use any of the new functionality
- Production downtime increased increase may be required
- Preliminary estimate and discussions with Lincoln indicated that additional downtime could fit within normal weekend window.
- Test the process multiple times before golive
- Test the process early in the project
- If longer outage is required, start discussing and planning early in the project
- Initial test results indicate longer time will be required. Very conservative estimate is ~70 hours (ex: Friday Noon - Monday 9am). Important to plan now, even if the additional time is not ultimately required.
- Final schedule will be based on additional test results to determine expected time, detailed plans (including cushion for unexpected events, time & schedule to validate, time to back-out & restore if necessary, acceptable risk mitigation, ...) for golive