- Definition of Enhance Packs
	
		- SAP's new approach to delivering new or enhanced functionality. Formerly included in support packs.
 
	
	 
	- Rationale for including Enhancement Packs in this year's support pack project scope
	
		- Avoid a separate project to add these enhancement packs
		
			- $240K IS&T effort
 
			- Production freeze
 
			- Business testing, validation
 
			- Production outage
 
			- Production validation
 
			- Literally a repeat of the support pack project
 
		
		 
		- Enhancement packs are a pre-requisite to new functionality
		
			- Required for Enterprise Learning Product - project sponsored by Training Alignment Team, HR, and approved by ASPCC
 
			- Required for other, newer SAP functionality that will be considered as part of 'Administrative System Roadmap'
 
			- See attachments for details of enhancement pack content for selected areas of potential interest to MIT. Full list is available here Support Documents.
 
		
		 
		- MIT Lincoln Lab and other higher ed & research SAP customers following the same strategy
 
		- Approach recommended by project team, approved by sponsor and steering committee.
 
	
	 
	- Risks & Mitigation
	
		- Enhancement Packs create problems with existing functionality used by MIT
		
			- Don't use Enhancement pack functionality until after year-end support pack project complete
 
			- Test all critical functions as part of the support pack project
 
			- Low probability since we don't use any of the new functionality
 
		
		 
		- Production downtime increase may be required
		
			- Preliminary estimate and discussions with Lincoln indicated that additional downtime could fit within normal weekend window.
 
			- Test the process multiple times before golive
 
			- Test the process early in the project
 
			- If longer outage is required, start discussing and planning early in the project
 
			- Initial test results indicate longer time will be required. Very conservative estimate is ~70 hours (ex: Friday Noon - Monday 9am). Important to plan now, even if the additional time is not ultimately required.
 
			- Final schedule will be based on additional test results to determine expected time, detailed plans (including cushion for unexpected events, time & schedule to validate, time to back-out & restore if necessary, acceptable risk mitigation, ...) for golive
 
		
		 
	
	 
                
        
    
         
                        
    
        
		
            
            
        
                        
    
        
                
    
            
 
    
    
    
    
    
    
    
    
        
            
            
    
    
        
            
            
    
 
 
 